Sutton residents packed a Select Board meeting to oppose the Kraft Group's $16 billion data center
The proposed campus would dwarf what Sutton has now
- $16 billion
- for the proposed data center campus
- 10
- buildings planned
- 2.5 million
- square feet at full buildout
- $2.8 billion
- assessed value of all existing Sutton property
Sources: The Boston Globe, Radio Worcester
If you live in Sutton, this one's close to home. More than 100 people packed Tuesday's Select Board meeting on the Kraft Group's proposed $16 billion data center campus, planned about 10 miles south of Worcester. It would have up to 10 buildings. All six speakers in the roughly 15 minutes of public comment opposed it.
Chair Jonathan Anderson said, "This is not a project that's a done deal." There's no application yet, and Sutton has no zoning rules for data centers. Board member Christine Watkins said of the rush before May's town meeting that "it could be a decision we live with forever."
- Deficit: about $350,000, projected at $2.5 million next budget cycle
- Deficit by 2033: about $10 million, per the town manager
- State permits: need local approval first, per Gov. Healey's executive order
Property taxes would climb to $27.8 million a year with all 10 buildings
Sources: The Boston Globe, Radio Worcester
View as table
| Value | |
|---|---|
| First two buildings, FY2031 | $10.4 million |
| All 10 buildings, 2035 | $27.8 million |