SuttonTop story
The Kraft Group has proposed a $16 billion, 10-building data center campus in Sutton
The campus would open in phases if it moves ahead
- Nov. 9Town manager sends the Select Board a memo on the proposal
- Nov. 10Select Board hears the proposal and takes no vote
- 2029First two buildings would open
- 2030-2033Two more buildings would open each year
Sources: WHDH, bostonglobe.com, CBS Boston, Worcester Business Journal
The Kraft Group and Unified Global Packaging Group have proposed a 10-building data center campus in Sutton, about 10 miles south of Worcester. It would draw about 900 megawatts and represent more than $16 billion in private investment, the developer estimates. The first two buildings would open in 2029, but no application has been filed.
Sutton's Select Board heard the proposal Tuesday night in a packed room. Chair Jonathan Anderson said, "This is not a project that's a done deal," and that the board plans multiple public forums. All six speakers during about 15 minutes of public comment opposed it.
- Property tax, FY2031: about $10.4 million a year from two buildings
- Property tax, FY2035: about $27.8 million a year from all 10
- Average home: about $2,300 less in FY2031, $5,800 less in FY2035
Town staff say a bigger tax base would lower the rate, since Sutton raises only what its budget requires. Their model assumes the developer pays full property tax.
Town staff estimate the campus would cut Sutton's tax rate
| With the campus | Measure | Without it |
|---|---|---|
| $8.83 | FY2031 rate per $1,000 | $11.78 |
| $5.68 | FY2035 rate per $1,000 | $12.05 |
Source: This Week in Worcester
The state has a say, too. Under Gov. Maura Healey's September order, no state permits can be issued for a data center without local approval and a community benefits agreement.