Six Central Mass. lawmakers want answers on the $16 billion Sutton data center plan
The Daily Worcester team
If you live near Sutton, you're not the only one asking questions. Six Central Massachusetts legislators sent letters Nov. 23 to National Grid, Aquarion Water Company of Massachusetts and two other agencies about the Kraft Group's plan and its effects on electric rates and water supplies.
“While many details of this proposed project are still unknown, there is a clear potential impact on our constituents' cost of living and quality of life.”
The plan: 10 buildings drawing 900 megawatts off Boston Road and Providence Road. Town Manager Austin Cyganiewicz called it tentative in a memo, adding that no application has been filed. The memo also says the average single-family home would pay about $2,300 less in FY2031 and about $5,800 less in FY2035.
Sutton homes would pay about $2,300 less in FY2031 and $5,800 less in FY2035
Source: CBS Boston
View as table
| Value | |
|---|---|
| FY2031 | $2,300 |
| FY2035 | $5,800 |
Residents aren't waiting. A citizens' petition needs 200 signatures to force a Special Town Meeting, and two residents collected enough. The planning board expects state guidance on data center rules by the end of this year.
- Special Town Meeting: 45 days after the petition is submitted
- Passing the ban: needs a two-thirds majority at that meeting
- Town budget gap: $300,000 now, projected to hit $10 million by 2033
Sutton's data center fight has moved fast since Nov. 10
- Nov. 10A packed Select Board meeting takes up the proposal.
- Nov. 12Shawn Buzzell and Sarah Osterman Stone join on a petition to ban data centers.
- Nov. 17The petition was to be filed at town hall, calling for a special town meeting.
- Nov. 23Six legislators send letters with questions about the project.
- 2029The first two buildings would open.
- 2033All 10 buildings would be online.
Sources: MassLive.com, CBS Boston, Worcester Telegram